Sterling Community Center Renovation

Overview

  • This project will renovate the existing Sterling Community Center and is part of the Sterling Public Facilities Master Plan initiated by the Board of Supervisors in 2012.
  • The renovated Sterling Community Center will occupy 20,700 square feet of space at its current location, an expansion of 2,000 square feet. The additional space will provide two new entry vestibules and will accommodate an enlarged full court gymnasium.
  • The Sterling Community Center’s extensive renovation plans will raise the split-level building to a single level, provide for new outdoor spaces and bring the facility standards up to date. 
  • Features of the center include a public lobby, fitness room, computer room, kitchen, teen gaming room, classrooms and an art room. 
  • When reopened, the center will be operated by the Loudoun County Department of Parks, Recreation and Community Services.
  • The outdoor space renovation will include a new patio area, a renovated pavilion and an outdoor amphitheater. 
  • To maintain public safety during the renovation, the existing playground will be closed throughout the project.
  • The project is estimated for completion in fall 2021.

Construction Progress Photos

Current Status: August 2020

  • In July, crews completed the installation of the geothermal system, reinforcement of the foundation of the existing building and underground utility work.
  • Work on storm lines and water supply lines from Enterprise Street to the building is ongoing.
  • Over the next several weeks, crews will begin to erect structural steel posts and masonry block at the gymnasium and rough-in for utilities.

Stay Informed About This Project

Related Documents

Contact Us

For more information about the Sterling Community Center Renovation project, contact the DTCI at 703-737-8624 or email the department.

Media Updates

Email Glen Barbour, Public Information Officer or call 703-771-5086.