Sign up to receive a text message or email when new bids are added!
Bid Number: RFQ 411782
Bid Title: Construction of the Philip A Bolen Mem Park Phase II - Concession & Restroom Facilities, RFQ 411782
Category: Procurement
Status: Closed
Additional Status Information: Bid Tabulation issued on November 17, 2021.

Description:

Due to restrictions surrounding the COVID-19 pandemic, public access to County facilities is extremely limited. The mailing of bids is preferred. However, if a bid is hand delivered, it will be received in the lobby of 1 Harrison Street, SE, Leesburg, VA 20175 ONLY in the Drop Box labeled: Procurement Bids and Proposals between the hours of 8:30 a.m. and 5:00 p.m.

ALL HAND DELIVERED BIDS MUST BE SUBMITTED AT THIS LOCATION PRIOR TO 4:00 P.M. on the Acceptance Date of the bid in order to be considered. Bids will not be accepted at any other building locations or after 4:00 P.M. Bids will be opened and announced by the Procurement Division staff via audio/video teleconference at 4:30 p.m. (Atomic time) on the Acceptance Date. To participate in the audio portion of the opening, please dial the number provided in the Instruction to Bidders and follow the prompts as designated. You may also witness the announcement of received bids as they are opened using GoToMeeting with the instructions included in the Instructions to Bidders

Please contact the Contracting Officer or Assistant Purchasing Agent designated on the front cover of the solicitation with any questions regarding this process. Bidders are strongly encouraged to check the County’s website routinely for updates.

The Intent of this Invitation for Bid (IFB) is for the County of Loudoun, Virginia (County) to obtain the services of a qualified General Contractor to construct the Philip A. Bolen Memorial Park Phase II - Concession and Restroom Facilities which includes four new permanent restrooms and concession facilities and other miscellaneous site improvements as required to update the existing facilities at the Philip A. Bolen Memorial Park (property pin #191-16-9866) located in Leesburg, Virginia at the intersection of Sycolin Road and Cochran Mill Road, in the Catoctin Election District. The new facilities include two (2) restroom buildings, one (1) single level concession and restroom building and one (1) two story concession and restroom building. Additional site improvements include the construction of 24 shade structures, trash enclosure and installation of site utilities to support the new buildings. In addition to the construction of the new facilities the demolition and removal of the existing six (6) ELOO buildings and connecting infrastructure is also required.

As this Project is being constructed within an active park, strict work hours have been established to minimize public interaction. Refer to Specification 011000 – Summary of Work for these restrictions.

The costs associated with the removal of any and all unsuitable soils and/or rock encountered below subgrade (as defined in Specification 312000), during the construction of this project shall be borne by the County. The County requests that the Contractor provide unit prices for unsuitable soils removal and rock removal. Unit Prices shall include the import of suitable material as needed to replace those quantities removed (It shall be assumed that suitable material will be procured from an off-site source). Unit prices shall be included on the Pricing Page of the Bid, and shall be multiplied times an assumed quantity provided by the County for an extended price. The extended price shall be carried by the County as an Owner’s Allowance in the final Contract Price and will be paid to the Contractor on a “per occurrence” basis, with any remaining allowance(s) being returned to the County upon completion of the project. This will apply to all excavations with the only exception being Drilling Activities (i.e. borings, geothermal wells, etc.). In these specific instances the Contractor should assume that rock will be encountered and price the drilling accordingly as part of their Base Bid Cost. Refer to Specification 312000 for soil classification and responsibility for all unsuitable soils and/or rock encountered above subgrade.

Furthermore, the Contractor will be responsible for the removal of all vegetation as required by the Contract Documents, to include, haul-off and disposal. Excess top-soil and spoils shall be removed from the site. Hauling and disposal of these materials shall be included in this Contract. Should the Contractor require the import of suitable materials to maintain the elevations and grades shown on the Contract Documents, then the Contractor shall be responsible for the costs of the suitable materials, inclusive of hauling, placement, and compaction.

The Contractor shall be responsible for all surveying to ensure the project is installed per the Plans and Specifications dated 7/13/21 and found at Attachment 5 (“Construction Documents”). Any deviations from the Contract Documents shall be specifically requested via Request for Information (RFI) submitted to the Architect/Engineer of Record. All deviations shall be noted in the Contractor’s “Record Set” of Construction Documents. Upon completion of the Project, two (2) hard-copy sets, and one (1) digital copy of “Record Set” Construction Documents shall be provided to the County.

Project Timeline: Substantial Completion of the entire project scope shall be achieved no later than 365 calendar days after Notice to Proceed is issued. Additionally, several restrictions are included as part of this Contract to minimize impacts to park operations. They are as follows:

• A1 facility and associated appurtenances: Specific to this facility, no on-site work can occur from June 16, 2022 through November 15, 2022.

• A2 facility and adjacent shade structures: Work on-site shall not start until the A4 facility and adjacent shade structures are complete. The A2 facility and adjacent shade structures shall achieve Substantial Completion no later than 365 calendar days after Notice to Proceed is issued.

• A3 facility and associated appurtenances: Shall achieve Substantial Completion no later than 365 calendar days after Notice to Proceed is issued.

• A4 facility and adjacent shade structures: Work on-site can start upon issuance of the Notice to Proceed and must be completed prior to starting work on-site for the A2 facility and adjacent shade structures.

• March 22nd through November 15th:

o Monday through Friday: No Contract Work Permitted After 4:30pm

o Saturday and Sunday: No Contract Work Permitted

• November 16th through March 21st:

o No Work Hour Restrictions

Please reference Specification 011000 “Summary of Work” for additional information regarding phasing and work hour restrictions.

Lastly, the County will require the Contractor awarded this Project to use e-Builder Construction Program Management Software. The County will purchase two (2) licenses for the Contractor’s use and will provide training for the Contractor to ensure proficiency as recommended by e-Builder. The license and training will be provided to the Contractor at no cost and prior to the issuance of Notice to Proceed. Further training due to a lack of proficiency will be the responsibility of the Contractor.

The e-Builder Construction Program Management Software will be utilized for all Project management documentation and correspondence, including but not limited to: RFI’s, submittals, meeting minutes, pay applications, proposed change orders/change orders, close-out documentation, etc. Contact e-Builder for further information at www.e-builder.net or 1-800-580-9322.

Pre-Bid Conference:

A Pre-Bid Conference will be held virtually using GoToMeeting software on October 1, 2021, at 11:00 am for clarification of any questions on the drawings, specifications, and site conditions. Until further notice bidders will not be able to participate in the Pre-Bid Conference in person. You must pre-register to participate in the Pre-Bid Conference by sending an email to . The subject line of the email should state “Register for Pre-Bid Conference for Philip A. Bolen Memorial Park Phase II - Concession and Restroom Facilities and the email should include the name of your firm and provide contact information to include phone number and address. Providing the email requesting participation in the Pre-Bid Conference was received prior to 1:00 p.m. the day prior to the date of the Pre-Bid Conference, the County will respond with the information to participate in the Pre-Bid Conference. Emails received after 1:00 p.m. will not be responded to. To participate in the audio portion only, dial the number provided and follow the prompts as designated. To participate by computer, connect to the link provided and follow the prompts as designated.

Addenda:

Addendum #1 Changes and/or Additions issued on October 8, 2021.

Addendum #2 Changes and/or Additions issued on October 25, 2021.

Addendum #3 Acceptance date changed to November 16, 2021 issued on October 29, 2021.

Publication Date/Time:
9/23/2021 9:00 AM
Publication Information:
Invitation for Bid
Closing Date/Time:
11/16/2021 4:00 PM
Bid Opening Information:
See Related Documents
Addendum Date/Time:
Addendum #3 issued on October 29, 2021.
Pre-bid Meeting:
October 1, 2021 @ 11:00 AM
Contact Person:
Kristy D. Varda, NIGP-CPP, CPPO, CPPB
Please see the attached document RFQ 411782 for additional contact information.
Download Available:
See Related Documents
Business Hours:
8:30 AM to 5:00 PM
Miscellaneous:
Addendum #3 Acceptance date changed to November 16, 2021 issued on October 29, 2021.
Related Documents:

Return To Main Bid Postings Page