Aug 05

Contractor Bidding is Underway for Lovettsville Community Center Construction

Posted on August 5, 2020 at 2:48 PM by Nancy McCormick

An invitation for bid for a general contractor to complete the construction of the new Lovettsville community center was issued on August 4, 2020. View the bid on the Loudoun County Division of Procurement’s bid posting page for details.

Phase one of the original construction schedule was completed in June 2020, including the sediment basin, riser structure, pond access road, fencing, and the temporary access road connecting East Broad Way to the gravel parking lot. The remaining four phases are delayed until a general contractor can be procured.

Construction is estimated to resume in late 2020.

The Lovettsville Community Center project will design and construct a new community center building in the Town of Lovettsville, replacing the existing building. The new community center will be over 15,000 square feet and will have a full-size gymnasium, five classrooms, a multipurpose room, a kitchen, administrative offices, meeting space and storage areas. The project also includes a 600-square-foot addition and renovation to the existing 1,200-square-foot Pool House.

For more information about the Lovettsville Community Center project, visit the project page.

Jun 04

Phase 1 of Lovettsville Community Center Construction is Complete

Posted on June 4, 2020 at 10:00 AM by Heidi Kellum

Work initiated at the end of March to finish the geothermal wells and parking lot for the Lovettsville Community Center has been completed. Phase 1 of the original construction schedule is now complete, including the sediment basin, riser structure, pond access road, fencing, and the temporary access road connecting East Broad Way to the gravel parking lot. 

Due to the termination of the construction contract in January 2020, the remaining phases of construction of the new community center are delayed until a contractor can be procured. Preparations for the contractor bidding process are underway.

Construction is estimated to resume in late 2020.

For more information about the Lovettsville Community Center project, visit the project page.

Mar 30

Loudoun County to Complete Lovettsville Community Center Parking Lot

Posted on March 30, 2020 at 9:32 AM by Heidi Kellum

On March 30, weather permitting, work is scheduled to begin at the Lovettsville Community Center project site to complete parking lot construction, earthwork and geothermal piping. This construction work will take approximately two months. 

Although the county is taking steps to finish projects in the area around the existing community center, construction for the new Lovettsville Community Center is delayed as the county works towards procuring a contractor, estimated for late 2020.

For more information about the Lovettsville Community Center project, visit the project page.