  • The Courts Complex Expansion project includes the design and construction of a new 92,000-square-foot Courthouse and renovation of existing Courts facilities, including new parking facilities.
  • The new Courthouse will be located on the current Church Street Parking Lot at the corner of Church Street and Edwards Ferry Road in downtown Leesburg. 
  • The existing Courthouse (18 East Market Street) and historic Valley Bank building (20 East Market Street) will be renovated.
  • Parking lots and pedestrian access to the Courts buildings will be improved. A new parking garage is being constructed at the existing Pennington Lot.

Drawing of planned new Courts Complex in downtown Leesburg looking northeast

Current Status: July 2019

  • Loudoun County hosted a public information meeting on the courthouse project on July 16, 2019 in Leesburg. The project design team briefed residents on proposed work slated for the complex. 
  • Loudoun County has issued requests for bids for construction of the new Courthouse. The bids are expected in by July 10, 2019.  
  • After receipt of the construction bids and award of the construction contract to the successful construction contractor, construction will begin in fall 2019. 
  • Construction is expected to take 30 months.